The Onshore LNG Facility
CCS JV will engineer and construct a 2-Train LNG Facility over a 5-year period, and will self-perform the majority of the works, while subcontracting works such as site preparation, civil and earthworks, and some temporary services and facilities.
Works which will occur within the first 12 months of the Onshore EPC contract are:
- Securing Permits for early construction works
- Commencing Engineering
- Procurement of main processing equipment
- Site preparation works
- Establishment of a temporary beach landing to barge goods to site
- Establishment of temporary facilities on site (offices, camp expansion, etc)
- Construction and fit-out of the on-site Training Centre